The Project

The Balboa Reservoir project is a public-private partnership with the City of San Francisco to develop a 17-acre parcel located adjacent to CCSF. Balboa Reservoir will transform land that was previously under-utilized as a parking lot into a vibrant new community affordable to a wide range of residents. We have worked closely with the community and surrounding stakeholders to develop this plan since 2017, significantly updating our initial proposal based on community and City input.

Phase IA of the plan is now underway, which includes the site infrastructure as well as two affordable housing buildings, E and A, identified on the plans below. Work started in November 2025 and is anticipated to be complete in Spring 2028.

Location

Phase IA

Features of Phase IA

  • Building E will offer 128 units of affordable housing. Construction will begin in Spring 2026 and is anticipated to be complete in Spring 2028.
  • Building A will offer 159 units of affordable housing. Construction will begin in Summer 2026 and is anticipated to be complete in Spring 2028.
  • New and Improved Mayor Edwin Lee Ave will connect the neighborhood directly to Ocean Ave. and includes protected bikeways and street trees.
  • New streets — Meyer Loquat and Wisteria — will form the loop road surrounding the future Balboa Reservoir Park.
  • Storm, sewer, and electrical infrastructure for the entire community are currently under development.

Note: Phase IA does not include Balboa Reservoir Park or public open spaces.

Full Site Plan

Features

  • 1,100 housing units, including 550 below market rate units available to low- and moderate-income households
  • Up to of the 150 below market rate units to be dedicated for educator households
  • At least 40% of units will have 2 or more bedrooms to accommodate families
  • Approximately 100 for-sale townhomes adjacent to Westwood Park

Renderings